Construction of protective structures in Poltava region continues

Construction of protective structures for critical infrastructure facilities continues in Poltava region. The readiness level of these structures ranges from 34% to 99%. Delays in construction are linked to prolonged air alerts and high demand for metal structures.

In brief

  • Construction of protective structures for 43 energy facilities is ongoing in Poltava region.
  • The readiness level of protective structures ranges from 34% to 99%.
  • Construction is taking place at 41 critical infrastructure facilities.
  • Delays in construction are caused by combat actions and air alerts.
  • The head of the regional military administration predicts a generation of about 650 megawatts in Poltava.
Covered by 3 of 6 media groups
  • Budget not in the collected reports
  • Public money 1 source
  • Media business 1 source
  • Big capital not in the collected reports
  • Readers and grants 1 source
  • Undisclosed not in the collected reports

No newsrooms from these groups in the collected reports: budget, big capital, undisclosed. 1 of 4 newsrooms not yet assigned to a group.

What are media groups?

Share of reports by media group
GroupShareCount
Public money
  • Newsroom 1
34%1 item
Media business
  • Newsroom 1
33%1 item
Readers and grants
  • Newsroom 1
33%1 item
Not classified yet—1 item

How we count media groups — Methodology

Who the outlets write for
  • community 2
  • region 0
  • country 1
  • world 0
Channels
  • Websites 1
  • Telegram 3

How we measure speed, distance and channels

Report an error

    • first item
    • earliest
    • local

    На Полтавщині рівень готовності інженерного захисту об’єктів критичної інфраструктури наразі становить від 34% (об'єкти життєзабезпечення) …

    • first item
    • caught up, 14 h later
    • local

    На Полтавщині триває будівництво захисних споруд для 43 об’єктів енергетики

  • Зміст. ПолтаваReaders and grants
    • first item
    • caught up, 14 h later
    • local

    Захисні споруди на об’єктах критичної інфраструктури Полтавщини готові на 34–99%.

  • NVMedia business
    • first item
    • caught up, 15 h later
    • national desk

    У Полтавській ОВА заявили, що захист критичної інфраструктури в області виконано на 34−99%